Tracking the lifespan of the San Diego expansion exposes years of shifting target dates, neighborhood confusion, and regulatory logjams. While city agencies cleared preliminary zoning requirements early on, follow-through remained sporadic.
| Timeframe | Announced Milestone | Ground Reality |
|---|---|---|
| 2016 | San Diego site acquisition announced | National Avenue property selected; community anticipation surges. |
| 2018, 2019 | Permit filings and architectural drafting | Minor lot preparations occur, followed by abrupt construction pauses. |
| 2021, 2023 | Post-pandemic reopening schedules promised | No heavy machinery active on site; initial permits approach expiration. |
| September 2026 | Reaffirmed commitment to open | Local media reports imminent movement despite visible lack of ongoing work. |
| October 2026 | Foreclosure auction initiated | Public filings confirm default exceeding $21 million in unpaid obligations. |